HomeMy WebLinkAbout58-24RESOLUTION 58-24
A RESOLUTION OF THE CITY COUNCIL OF THE TOWN OF LOS ALTOS HILLS
ACCEPTING THE 2024 PAVEMENT REHABLITATION AND DRAINAGE
IMPROVEMENT PROJECT AS COMPLETE, AUTHORIZING FINAL RETENTION
PAYMENT TO THE CONTRACTOR, AND DIRECTING THE CITY CLERK TO FILE
NOTICE OF COMPLETION
WHEREAS, on May 16, 2024, the City Council approved the Plans and Specifications for the 2024
Pavement Rehabilitation and Drainage Improvement Project; and
WHEREAS, on July 18, 2024, the City Council adopted a resolution awarding the contract to
O'Grady Paving, Inc. for $1,227,238.50; and
WHEREAS, the project was completed according to the Plans and Specifications on October
25, 2024; and
WHEREAS, staff recommends that the City Council accept the project as complete and authorize
the remittance of the 5% percent retention 35 days following project acceptance.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the Town of Los Altos Hills that:
Section 1. The 2024 Pavement Rehabilitation and Drainage Improvement Project is
accepted as complete, and the appropriate officer of the Town is authorized to make final
payment.
Section 2. The City Clerk is directed to file with the County Recorder of Santa Clara
County, notice of the completion of said project within ten (10) days from the date of this
Resolution.
The resolution was passed and adopted by the City Council of the Town of Los Altos Hills at a
regular meeting held on 21 sc day of November 2024 by the following vote:
AYES: Mok, Schmidt, Swan, Tankha, Tyson
NOES:
ABSENT:
ABSTAIN:
BY: